In the third section of the sixth stage, the floor slab of the last floor is cast
RIEL Real Estate Corporation reports that in the third section of the sixth stage of Velyka Brytaniia RC, the floor slab of the last floor is cast, the brickwork of the walls and interior partitions of the sixth floor is underway. This was announced by the construction project manager Oleh Melnyk.
It is also reported that in the second section, finishing and insulation of the facade, as well as insulation and waterproofing of terraces are in progress.
In the fourth section, the monolithic works of non-residential premises have been completed.
You can always find out more about construction progress from RIEL service managers.